🔧 Bearspaw South Feeder Main — Reinforcement complete April 2026. The critical pipe supplying ~60% of Calgary's treated water failed in June 2024 and again Dec 30, 2025. Parallel replacement main under construction, expected end of 2026. City update →

River Flow — Real-Time Stations

Bow River at Calgary
05BH004
Bow
Discharge
m³/s
Level
m
Elbow R. below Glenmore Dam
05BJ001
Elbow
Discharge
m³/s
Level
m
Elbow R. at Bragg Creek
05BJ004
Elbow upstream
Discharge
m³/s
Level
m

Reservoir Storage

Bearspaw Reservoir
Bow River · TransAlta / City of Calgary · run-of-river

Bearspaw is a run-of-river reservoir with limited storage capacity — inflows from the Bow frequently exceed it. Real-time storage data is not published by Alberta Environment. Upstream flow at 05BH004 is the best available public proxy. The City draws drinking water from Bearspaw WTP for the northwest system.

Glenmore Reservoir
Elbow River · City of Calgary WTP · 05BJ008
Loading… Max: 23,502 dam³

Station & Infrastructure Map

Flow Profile — 7-Day History

Scale:

Calgary Dual-Source Water System

Bow River (05BH004)
Bearspaw Reservoir
Bearspaw WTP
⚠ Feeder Main (PCCP 1970s)
NW Distribution
Elbow R. (05BJ004 upstream)
Glenmore Reservoir (05BJ008)
Glenmore WTP
05BJ001 (below dam)
SW Distribution

Infrastructure Context — Bearspaw South Feeder Main

Two catastrophic failures in 18 months — and a $342M reckoning

The Bearspaw South Feeder Main is the most critical single pipe in Calgary's water network, carrying approximately 60% of the city's treated drinking water from the Bearspaw Water Treatment Plant into the distribution system. Installed in the mid-1970s as prestressed concrete cylinder pipe (PCCP), it was first flagged as a high-consequence risk in 2004 — but recommendations to inspect, monitor, and rehabilitate it were deferred across multiple councils and management cycles for 20 years.

2004
Risk formally identified after a feeder main rupture in northeast Calgary
2017 · 2020 · 2022
Three separate recommendations to inspect the Bearspaw feeder main deferred or redirected
June 2024
First catastrophic rupture floods Trans-Canada Highway. City begins concrete encasement repairs and installs acoustic fibre-optic monitoring (1 million sensing wires).
December 30, 2025
Second catastrophic failure ~1 km from the June 2024 break. Pipe splits in a "zipper" failure with no warning. 13 people rescued from icy floodwater. City-wide conservation order issued.
January 2026
Independent panel report: city ignored 20+ years of warning signs. Council votes unanimously to implement all recommendations.
April 2026
Emergency reinforcement completed. Parallel replacement main under active construction.
2027–2030
$342M remediation program proposed — nearly double the $168M spent 2023–2026. Provincial cost-sharing requested.

Calgary's dual-source design — Bearspaw WTP drawing from the Bow, Glenmore WTP from the Elbow — is both a strength and a vulnerability. When Bearspaw is compromised, the Elbow/Glenmore system cannot fully compensate. This is why the flow readings at 05BH004 and 05BJ001 are not just environmental monitoring: they are directly linked to Calgary's most pressing infrastructure story.